About us
-
About us
Downer is listed on the Australian Securities Exchange and employs more than 31,000 people.
Learn more
-
-
What we do
-
What we do
Downer is a leading provider of integrated services in Australia and New Zealand.
-
-
Investors
-
Investors
View our latest ASX announcements as well as financial reporting, key dates and shareholder information.
Learn more
-
-
News and media
-
News and media
View the latest news from Downer as well as our capability brochures.
Learn more
-
-
Sustainability
-
Sustainability
We understand the importance of having a responsible and forward-thinking approach to sustainability.
Learn more
-
-
People and careers
-
People and careers
Our people are fundamental to the culture and success of Downer.
Learn more
-
-
Contact us
-
Contact us
Downer has over 300 sites across Australia and New Zealand with our head office based in Sydney.
Learn more
-
Downer Case Study
Restoring Florentine Bridge in TAS
27/06/2022
There’s a lot you need to be prepared for when you’re building a 27-metre-long bridge in Tasmania’s remote wilderness.
The limited mobile coverage. The cold and often unpredictable weather. The rising water levels of the river. The special equipment needed for the environmental conditions. And, don’t forget the logistics of moving 27-metre-long concrete Super T beams through tight winding gravel roads.
This was all in a day’s work for the VEC team that has just completed replacing the Florentine Bridge for Sustainable Timber Tasmania.
The new bridge has restored the forestry road link between Maydena and Wayatinah after the original bridge was deliberately burned in an act of vandalism in June 2016.
“Working remotely means you need to be really well organised,” said project manager Paul Menheere.
Parts of the new bridge, including the bridge deck, were constructed in-situ while the Super T beams were pre-cast in VEC’s manufacturing facility in Ulverstone and transported to the site. VEC has the ability to construct Super T beams up to 30 metres long.
Transporting the 27-metre-long Super T beams for the Florentine Bridge required a long combination vehicle, comprised of a prime mover and a dolly.
“The dolly needed to be steered manually to manoeuvre the beams around the tight corners for the last few kilometres of the road into the site,” said Paul.
“We also had another truck on hand to help if the prime mover got stuck on the gravel road.”
The team used a launching gantry to erect the beams. A launching gantry is used when there is restricted access for cranes. In this case, there was not enough room to set up a large crane on either side of the river.
“We don’t often have the situation where there isn’t room for a crane and we need to use the launching gantry,” said Paul. “It’s probably been about 10 years since we’ve needed to use it.”
There were a few other challenges to contend with on this project including the rising level of the river during winter and working in close proximity to the intake of a nearby salmon farm.
Work needed to be limited to the salmon farm’s shutdown period to avoid compromising the quality of the waterway, which could affect the sensitive fish breeding habitat.
Construction of the bridge was completed in early 2022.
Categories
Related articles
-
07/07/2022
Dam fine work provides outcome in Tasmania
Read more -
07/07/2022
CampbellTown underpass update
Read more -
01/07/2022
Trains & bikes: How our team at Maryborough are having a wheely good time
Read more -
05/06/2022
Downer wins Tibooburra Airport Contract
Read more -
10/04/2022
DM Roads deliver Australian first surface solution
Read more -
24/03/2022
Peter celebrates 50 years at Downer
Read more -
17/03/2022
Roads Services Pavement Team rebuild flood damaged roads
Read more -
15/03/2022
The women behind Melbourne’s Bigger, Better Trains
Read more